See what's been happening on site at Mell Gardens Stage 2
See what’s been happening at Mell Gardens Stage 2, where Metrocon is delivering 41 villas for the growing over-55s community in Spearwood: https://www.linkedin.com/feed/update/urn:li:activity:7472448786015903745
Captured in early May, momentum has picked up across the development, with multiple trades active across all four stages:
- Stage 1 (7 units): Roof cover and roof plumbing underway, with internal plastering preparation commencing shortly.
- Stage 2 (11 units): Brickwork and roof framing complete, with electrical and plumbing rough-ins underway.
- Stage 3 (14 units): Following successful slab pours, brickwork already 80% complete.
- Stage 4 (9 units): Footings in place for the final slab pours scheduled for the coming week.
We’re proud to be driving this project forward alongside our valued partners at Aegis Aged Care Group and Montague Grant Architects. Stay tuned for more updates as Mell Gardens Stage 2 continues to take shape!
Videography by Sommerset Studios (Luke Lategan).